From the official data
Post-Earthquake Production and Debris Management: Development Agency Records
DOĞAKA's 2025 Activity Report records that a 1,125 m² common production facility was built for the Antakya Tanners' Estate destroyed in the earthquake, that Hatay YİKOB's earthquake-debris processing project was contracted under the 2025 CMDP, and that the private-sector Green Transformation Technical Support Programme received 8 applications (6 successful).
| Indicator | Value | Year | Source |
|---|---|---|---|
| Antakya Tanners' Estate: common-use facility (m²) | 1,125 | 2025 | [1] |
| Leather Common Production Facility: status | Licence done; transfer approved; electricity connection pending | 2025 | [1] |
| Processing Earthquake Debris with Zero-Waste Awareness (YİKOB, 2025 CMDP) | Contract signed; tender preparations under way | 2025 | [1] |
| Green Transformation Technical Support Programme: applications · successful | 8 · 6 | 2025 | [1] |
| Furniture-sector development axes support programme | Not implemented; removed from the 2026 programme | 2025 | [1] |
What does this data mean for an investor?
The records show post-earthquake recovery moving at two speeds: a common facility for small-trade production has been built and is nearly ready (electricity connection pending), while debris recycling is still before tender. Debris processing shows the public side starting the process for a demolition-waste recycling investment; but debris volume, plant capacity and revenue model (gate fees, secondary-product sales) are not in this source (interpretation). The furniture support programme not being implemented suggests not relying on a ready support channel in that sector.
Limitation: The source is the development agency's own activity statement; project statuses relate to the period of the report and may have changed. It contains no amount, capacity or debris-volume data.